The work on the Lagos axis of the Lagos-Ibadan standard gauge rail means that construction has fully started on the project.

According to the Nigerian Railway Corporation, NRC which disclosed this to newsmen in Lagos on Wednesday, the work started after the challenges of underground pipelines and cables were resolved.

Mr Jerry Oche, Lagos District Manager of NRC, told newsmen that work had started on the laying of standard rail gauge from the Lagos axis.

Also Read: (VIDEO) Shayi-Shayi Gang: Shocking Confessions Of Kano Drug Addicts

“We all know that the standard gauge in Lagos axis from Apapa to Ijoko in Ogun is in the same corridor with narrow gauge.

“Now, so far so good, the government is serious about delivering the project at the scheduled time and there is increase in pace of work along the Lagos axis.

“The project has been concentrated outside Lagos because of the underground cables and pipelines challenges in the city.

“But all have been resolved now and work has started wholly in the axis,' Oche said.

According to him, water pipelines, cables and other installations underground of public utilities had posed great challenge to the execution of the work in Lagos.

The NRC district manager said that some of the railway staff quarters were also affected by the construction.

He said that the corporation had paid the affected staff members a year’s accommodation rent to secure alternative housing pending when the new quarters constructed for them would be completed.