Lagosians are you ready for an impending darkness in the land?

The darkness will last at least seven days as the Ikeja Electric (IE) Plc will interrupt power supply in some parts of the state from November 3 to November 10.

Felix Ofulue, the Head, Corporate Communications, said in a statement in Lagos that the company would carry out a complete rehabilitation of the Maryland Injection Substation.

Also read: Supreme Court Halts Liberia's Presidential Run-Off

“The rehabilitation will affect power supply to Mende, Anthony, Maryland, Ikeja GRA, Shonibare Estate, Part of Ojota, Ketu, Ikosi, Demurin and environs.

“Power supply will be restored immediately after the completion of the exercise.

“I solicit the understanding and cooperation of all our consumers that would be affected by this outage,’’ he said.

Ofulue added that the rehabilitation will not exceed the planned period of time.